Skip to the story | Text edition home | Full site

Reported by us | Carver

Carver Planning Board lets two solar farms drop battery storage; Federal Pond plan still pending

Both projects qualified for net metering, a lawyer for the developers said, and the board added that any battery plan would have to come back for review. Federal Pond Solar's hearings resume Nov. 18 and Dec. 8.

By the SC360 Breaking and Public Safety Desk | Published Nov. 15, 2026 | Last verified Nov. 15, 2026, 3:50 p.m. ET

CARVER Two permitted Carver solar farms will be built without the battery storage systems they once planned, after the Planning Board approved the changes Tuesday, Nov. 10.

The board approved minor modifications for Fuller Street Solar, at 0 Fuller St., and Plymouth Street Solar, at 204 Plymouth St., both in residential agricultural zones. Greg Sampson, a lawyer with the firm Sullivan & Worcester who spoke for the developers, said each project qualified for the net metering program, which makes battery storage less essential, and both are nearing construction. He said the battery system is coming out of the Fuller Street plan for now. "We don't have plans to put one on the site at this point," he said.

Carver already has rules for battery storage: a section of its zoning bylaw adopted at the April 2023 annual town meeting requires a special permit and site plan review for systems of 0.5 megawatt-hours or more. Lakeville voters take up a battery storage bylaw at their special town meeting Wednesday, and Lakeville's guide to that meeting says the state requires cities and towns to adopt such a bylaw by the end of 2026. In Carver, a third project that pairs solar panels with batteries on a cranberry bog property at 104 Tremont St. is still under review.

What changed

At Fuller Street, the developer also moved its equipment staging area to a spot the property owner had already cleared, closer to the array, trimmed an area that had been marked as part of the work zone where no work was planned, and shifted access roads to follow roads already on the site. Chair Alan Germain read a comment from the deputy fire chief that the changes are minor and will have no impact on public safety.

At Germain's request, the approval will say that if battery storage comes back, the developer must return to the Planning Board for another review. Town Planner Sean Lewis said there is really no change to the project other than the battery system being removed.

When a resident asked about taking the array down at the end of its life, Germain said the decommissioning amount is already set in the original approval and is not changing. Carver's zoning bylaw requires large solar projects to post an escrow covering 75% to 125% of the cost of removal, in an amount the Planning Board finds reasonable, and to be removed within 120 days after they stop operating. If an owner does not remove an abandoned array, the town may remove it and charge the property owner.

Plymouth Street Solar, permitted together with Fuller Street and held by the same owner since, also qualified for net metering and dropped its batteries, Sampson said. A surveyor corrected a property line that was wrong on the original plans, and the developer added two arrays inside an area already cleared, a small increase in footprint. An elevated road through a decommissioned upland cranberry bog will be lowered along about 150 feet so the panels can sit above it, and some areas that had grown back since earlier clearing will be cleared again inside the approved work limits.

Sampson said the panels could be removed at the end of the project's life and the bog restored. Asked by member Kevin Robinson whether the added panels change the decommissioning amount, he said removing the batteries would probably offset them and the developer could run that number before pulling the permit. Lewis said the project has been submitted to the Conservation Commission and its chair has been asked whether the bog road change needs a minor modification there, a question apart from the Planning Board's decision. The board approved both modifications by voice vote, with no one voicing opposition.

Federal Pond Solar still under review

Federal Pond Solar LLC is seeking a special permit and site plan approval to build ground-mounted solar and dual-use solar arrays, which share the land with farming, with coupled battery storage at 104 Tremont St. The developer asked the Planning Board to continue that hearing to Tuesday, Dec. 8.

The same project is before the Conservation Commission, which is reviewing work within land subject to flooding and wetlands tied to a cranberry bog, and within the buffer zones around them. That hearing was first set for Aug. 19, and the commission's Nov. 4 meeting was canceled for lack of business, with the hearing continued to Wednesday, Nov. 18. The commission meets in Meeting Room 1 at Carver Town Hall, 108 Main St., where its hearings on the project have been noticed for 7 p.m.

The Planning Board also continued to Dec. 8 a site plan review for NLE Charging LLC, which wants to add eight electric vehicle charging spaces, four of them accessible, with a canopy, in an existing commercial parking lot at 2 Montello St. The same night, the board voted 5-0 to close its public hearing on the Smart Growth zoning district headed to the Dec. 1 special town meeting.

What happens next

The Planning Board meets Tuesday, Dec. 1, at Carver Middle High School before the special town meeting, and Tuesday, Dec. 8, at the Carver Police Station, where the Federal Pond Solar and NLE Charging hearings resume. Area 58 TV records the board's meetings. Residents can reach the Planning Board at 508-866-3450 and the Conservation Commission at Carver Town Hall, 108 Main St., 508-866-3405, and the Carver Planning Department posts its updates on Facebook.

Label: Reported by us, from the town's posted records.

Notes

Every fact comes from the Area 58 recording of the Carver Planning Board's Nov. 10 meeting, the board's revised Nov. 10 agenda, the Carver Conservation Commission's Nov. 4 notice, the town's Planning Board directory, Carver's zoning bylaw and Lakeville's guide to its Nov. 18 special town meeting. We read them on Nov. 14 and 15, 2026. Quotes are as spoken at the meeting, checked against the recording's caption track. We checked each date and weekday against a calendar. Not heard: we did not ask the developers or the town for comment for this story; the developers' lawyer is named as he introduced himself at the meeting, with the spelling from his firm's profile.

Corrections

No corrections to this story. If something here is wrong, tell us. Every correction is dated on the story and listed in our public log.

Sources (7)

  1. Area 58 Carver, Carver Planning Board, November 10, 2026 (recording)Recording of the Tue. Nov. 10, 2026 meeting, 1:03:39, posted Nov. 11, 2026, read from its caption track. Fuller Street Solar about 5:46 to 11:59; Plymouth Street Solar about 12:11 to 19:00; continuances 19:21; 40R hearing closed 53:24. Read Nov. 14 and 15, 2026.
  2. Carver Planning Board, revised meeting agenda, Nov. 10, 2026, 6:30 p.m., Carver Police StationTown of Carver Agenda Center. Items 3 and 4, Fuller Street Solar and Plymouth Street Solar minor modifications; item 5, Federal Pond Solar, 104 Tremont St., continued to Dec. 8; item 6, NLE Charging, 2 Montello St., continued to Dec. 8; future meeting dates. Read Nov. 14 and 15, 2026.
  3. Carver Conservation Commission, Nov. 4, 2026 meeting notice (canceled)Town of Carver Agenda Center. Meeting canceled for lack of business; Federal Pond Solar notice of intent, 104 Tremont St., DEP file SE126-710, continued to Nov. 18, 2026; commission phone. Read Nov. 14 and 15, 2026.
  4. Town of Carver, Zoning Bylaw (Chapter 290), 2024 editionSection 290-3-6.6, solar removal within 120 days, abandonment, removal costs charged to the property owner, surety of 75% to 125% of removal cost; Article 3-7, Battery Energy Storage Systems, added April 11, 2023 annual town meeting, Article 28, Tier 2 and Tier 3 systems (0.5 MWh and up) need a special permit and site plan review. Read Nov. 15, 2026.
  5. Town of Carver, Staff Directory, Planning BoardAlan Germain, chair; Kevin Robinson, member; Sean Lewis, town planner; Planning Board phone 508-866-3450. Read Nov. 15, 2026.
  6. Legal 500: Gregory Sampson, Sullivan & Worcester LLPSpelling of the name of the lawyer who introduced himself on the recording as Greg Sampson of Sullivan & Worcester; leads the firm's permitting and land use group. Read Nov. 14, 2026.
  7. Town of Lakeville, Resident's Guide, Nov. 18, 2026 Special Town MeetingArticle 6, Battery Energy Storage Systems bylaw, and the town's note on the state deadline. Read Nov. 14, 2026.

This story on the full site