Fall River has not lined up money to put permanent boilers in the vacant Bank Street Armory, the city administrator told The Herald News last week, after city councilors pressed the administration on Nov. 17 to heat the city-owned building before winter.

Director of City Operations Al Oliveira told the City Council's Committee on Real Estate, Facilities and Housing on Nov. 17 that three high-efficiency boilers are available now and that his quotes, about $90,000 with installation, are good for about 30 days. Removing the plants growing from the building would cost about $40,000 more, he said. "I can't do anything without funds," he told the committee.

City Administrator Ann O'Neil-Souza said at the meeting that she would take the request to Mayor Paul Coogan, and the committee tabled the item. Three days later, she told the paper that, to her knowledge, the administration had not identified money for the work and that its priority is keeping up buildings that people use. City Council Vice President Michelle Dionne, who chairs the committee, told the paper the same day that she had heard nothing from the administration about the heat.

What the heat would cost

Oliveira said Liberty brought a new gas line into the building at no cost to the city, and a new gas meter is now outside. Boilers like the ones the city usually installs would take about 16 weeks to arrive, he said, so he priced three high-efficiency boilers that can be had now, about $45,000 of the total. The $90,000 also covers installation, the tie-in to the old piping and radiators, and a plumber checking each unit ventilator in the building. He said temporary heat costs more in the long run.

Oliveira's two figures add up to about $130,000. Alexander Silva, president of the Preservation Society of Fall River, asked councilors to pass a resolution asking the administration for the money for both jobs, a total he put at about $135,000. He said money for the heat had been sought in the last budget but the line "was eventually either moved or reallocated or deleted." "We're kind of at an impasse for funding," Silva said.

Why grants have not covered it

O'Neil-Souza told the committee the city applied for $250,000 through the state's underutilized properties grant and the armory was not chosen. She said the city's grant writer believes that, without a federal or other earmark, grants are unlikely to cover the work, even the heat. Capital money has gone to other projects first, she said, including the parking garages, fire stations and the Lewiston Street building, with federal pandemic relief money and loan orders going to buildings people occupy.

Silva said Community Preservation Act money might pay for the boilers. That would be up to the committee that weighs CPA requests, he said, but because heat is integral to preserving the outside of a historic building, the boilers would probably qualify, as heating and cooling units tied to facade work did at the Central Fire Station. The vegetation was cleared once before, two years ago, with an emergency CPA grant, he said. The new CPA round has just begun and will be reviewed early next year, so the armory would need an out-of-cycle application or would wait until next September.

Eligibility applications for the current CPA round were due Sept. 9, and funding applications are due Feb. 4, 2027. The city's Community Preservation Committee, which recommends CPA spending to the City Council, meets on the third Monday of the month except in December and July, and no CPA project can start until the council gives final approval.

Councilors push back

Dionne said the committee has made clear in its minutes, more than once, that it wants heat in the building. "Honestly, in a 400 and some odd million dollar budget, $90,000 is a drop in the bucket," she said. She noted that the Central Fire Station work is being paid for with a bond, that federal pandemic relief money went into the Lewiston Street building and that the council bonded for the parking garages, so none of that came out of the city budget.

Councilor Paul Hart, who said he voted to sell the armory when a sale came before the council, said the building needs permanent heat but that the city would do better selling properties like it to people who can take them on. "We're not good at real estate in the city. We're just not," he said.

Councilor Shawn Cadime said the committee talked about heating the armory at its March 12 meeting. "If this was either one of our residents or a commercial property that we owned, I don't know that we would be waiting eight months to make a determination as to whether or not we're going to put in permanent heat into a building," he said. "I personally just feel that the Bank Street Armory is not a priority. I don't know why it's not a priority." The council has not authorized a sale, he said, so the city has to maintain it.

"It shouldn't be the city council's responsibility to ask the administration to request money from us," Cadime told Oliveira. Oliveira said he had asked the city's chief financial officer for the money on numerous occasions and would follow up the next morning. "Right now it looks like I'm the one that's in jeopardy because I didn't do what I was asked to do," he said.

A study comes first

Silva said the city has $85,000 in grants for an existing conditions assessment and a feasibility study of the best use for the building, and the request for qualifications was close to going out to bid. The work should be underway by spring and done next summer, he said, and a 2015 study looked only at accessibility, not at how the building could be used.

O'Neil-Souza said the mayor supported selling the building when the city last offered it, and that the offer drew one response that did not win approval. In January 2024, the council rejected a sale to a developer who wanted to turn the armory into market-rate housing, The Herald News reported.

What happens next

No order for armory money was on the agenda for the City Council's Nov. 24 meeting, and the committee can take the item off the table at a later meeting. Oliveira's quotes, good for about 30 days from the Nov. 17 meeting, would run out in mid-December. O'Neil-Souza said she would tell the mayor that the council is looking for an order from him to transfer and appropriate money for the boilers and the vegetation work. Under state law, the council can also vote to ask the mayor for a written recommendation for money that is not in the budget; if none comes, it can make the appropriation itself after seven days by a vote of at least two-thirds of its members.

Residents can reach councilors through the City Clerk's office, One Government Center, 508-324-2220, and the Community Preservation Committee at cpc@fallriverma.gov or 508-294-5344. South Coast 360 asked Mayor Coogan's office on Tuesday, Nov. 24, whether he plans to send the council an order for the boiler money. The office had not answered by Saturday morning, and we will add the answer here when it comes.

Label: Reported by us, from the town's posted records.

Notes

Every fact comes from the city's own recording of the Nov. 17 Committee on Real Estate, Facilities and Housing meeting on Fall River Government Television, the city clerk's Nov. 24 City Council agenda packet, the city's 2026 council committee list and Community Preservation Committee pages, Section 33 of Chapter 44 of the state's General Laws, and, where credited, The Herald News. We read them on Nov. 24, and we checked each date and weekday against a calendar. The boiler and vegetation total is added from the figures Oliveira gave. The mid-December date counts 30 days from the Nov. 17 meeting. South Coast 360 asked Mayor Paul Coogan's office by email on Nov. 24 whether he will send the council an order for the money; the office had not answered by Saturday morning, Nov. 28.

Corrections

No corrections to this story. If something here is wrong, tell us. Every correction is dated on the story and listed in our public log.

Sources (6)

  1. Fall River Government Television: 11.17.2026 City Council - Real Estate, Facilities & HousingRecording of the Nov. 17, 2026 committee meeting, posted Nov. 17, 2026. The armory item runs from about 0:01:30 to 0:33:00: Silva on the budget line and the resolution at 0:05:00 to 0:06:00 and 0:23:54 to 0:24:20; Oliveira on the gas line, boilers, $45,000, $90,000 and 30-day quotes at about 0:07:30 to 0:09:00 and 0:23:00 to 0:24:00; Dionne at 0:12:55 to 0:13:58; Hart at 0:14:00 to 0:16:40; $40,000 vegetation at 0:18:38; Silva on CPA at 0:19:13 to 0:20:15; O'Neil-Souza on the $250,000 grant, the grant writer and the mayor at 0:11:30 to 0:13:00 and 0:20:49 to 0:21:42; Cadime and Oliveira at 0:26:19 to 0:32:23; tabled at 0:33:00. Read Nov. 24, 2026.
  2. The Herald News (Nick Rommel): Fall River Bank Street Armory heating system install still uncertainPublished Nov. 23, 2026. Credited for O'Neil-Souza's and Dionne's Nov. 20 statements and the January 2024 council vote. Read Nov. 24, 2026.
  3. City of Fall River: City Council agenda packet, Tuesday, Nov. 24, 2026Scanned packet, 117 pages: committee reports and orders on the Pearl Street garage; no armory heating order; Councilor Paul B. Hart named on a filed resolution. Read Nov. 24, 2026.
  4. City of Fall River: 2026 City Council committeesLists Vice President Dionne as chair of the Committee on Real Estate, Facilities and Housing. Read Nov. 24, 2026.
  5. City of Fall River Community Preservation Committee: Dates, Deadlines and Application PaperworkFY28 eligibility applications due Sept. 9, 2026; funding applications due Feb. 4, 2027; guidelines say no project starts before City Council approval. Meeting schedule and contacts on the committee page. Read Nov. 24, 2026.
  6. Massachusetts General Laws, Chapter 44, Section 33The council's power to appropriate by a two-thirds vote when the mayor sends no recommendation within seven days of its request. Read Nov. 24, 2026.