A short sample panel of a brick-print sound wall stands on a conference table in front of a man in a navy and white jacket reading papers, with other men seated at the table and a wall TV showing a video call behind them
A sample of the brick-print composite sound wall that Somerset Energy Storage LLC expects to use at 1606 Riverside Ave. sits at the front of the room during the Somerset Zoning Board of Appeals session at the Fairfield Inn and Suites on Wednesday, Nov. 18, 2026. Image: Somerset Access Television broadcast

Somerset's Zoning Board of Appeals voted 3-0 Wednesday night to approve the battery storage plant planned on the former Montaup power plant land, pending the members' review of the final written conditions.

The board's three voting members, including Vice Chair Bernard Miranda, who made the motion, each voted yes on a roll call near the end of a session of more than two hours at the Fairfield Inn and Suites on G.A.R. Highway. Somerset Energy Storage LLC, the company behind the project, sought a planned development permit under Section 6.10 of the zoning bylaw for the site at 1606 Riverside Ave., Assessor's Map B2, Lot 203.

The project, Salt Cod Energy Storage, is led by Flatiron Energy and would store up to 672 megawatt-hours of electricity to supply the grid at times of high demand, according to the town. The board has heard the petition at 12 sessions since April 9.

The vote brings the zoning board near the end of a review that has centered on fire safety and on how far toxic gas from a battery fire could travel toward the Stevens Street neighborhood. Other permits, including a stormwater permit from the Planning Board and the building inspector's demolition and building permits, still lie ahead.

What the board approved

The motion granted the permit together with the conditions discussed and revised at the table Wednesday. It added two conditions the town administrator had asked for, according to a speaker at the board's table: a mutually acceptable payment in lieu of taxes, or PILOT, agreement between the company and the town, and a second mutually acceptable agreement between them, with neither one finished yet. Earlier in the night a company representative said the host community agreement with the town is still being negotiated.

The motion also requires the planting and screening the zoning bylaw calls for between the site and its neighbors, as shown on the company's plans, and waives the bylaw section that allows one entrance and one exit on each street, none more than 35 feet wide, after a speaker at the table noted the fire chief may want a second entrance on Riverside Avenue. Before the vote, one member said that when conditions have changed substantially on past petitions, the board has voted on a clean, final copy, and asked to do the same here, and the board took up a suggestion made at the table to approve the permit now, subject to the members' review of the final written conditions.

What the reviewers said

The two outside firms the board retained to review the project told members their comments had been answered. A reviewer from Jensen Hughes said all 13 of the firm's comments on the plume study had been closed, and that the farthest the study found hydrogen fluoride reaching was about 91 feet from a battery enclosure, short of the nearest home. In its final memo, Jensen Hughes wrote that its review was based on the documents, that it did not rerun the computer models itself, and that two of the 13 comments, on weather inputs and model grid checks, were closed on the explanations of Hazard Dynamics, the company's plume consultant, because the underlying results were not provided.

A reviewer from Roux, the environmental firm working for the town, said Roux had issued 50 technical comments and that all had been resolved directly or could be handled through conditions, and that, within the zoning board's jurisdiction and at this stage of the project, the documents it reviewed are protective of public safety, health and welfare.

The company's lead presenter said none of the final edits to the plume study changed its results, the fire department's findings or its response tactics. A member said the fire chief and the police chief had both sent conditions, and a company representative said the fire conditions are nearly word for word from Fire Chief Jamison Barros' letter and that the chief had reviewed the edits.

The sound wall

The company brought a sample of the sound wall, a hollow composite panel printed to look like brick that a representative of VHB, the firm that did the noise modeling for the company, said is built to trap sound rather than bounce it back. The 24-foot wall has been moved back from where the first plans put it, and it will sit at least 50 feet from Stevens Street at the Riverside Avenue end, with the gap growing to more than 100 feet toward County Street, the project team said. A board member said Jensen Hughes agreed that, with the wall, the plant will meet the state's noise limits and the town's noise bylaw, and the project team said the model checked every address, at the property line and at second floor height.

Conditions changed at the table

Members spent more than an hour going through the company's draft conditions line by line. Among the changes:

  • Somerset police will have live access to the site's security camera feed, and the ability to record it, during construction and operation, as far as is technically feasible.
  • The final soil management plan, and any revision to it if contamination turns up, for example along the old No. 6 oil pipelines, will be reviewed by a qualified environmental professional working on the town's behalf and procured by the company.
  • Portable gas monitors for the fire department will be bought by the department with money from the company, not taxpayers, which the company said it intends to provide through the host community agreement.
  • The window for a town reviewer to answer a future submission before it is considered approved was lengthened from 30 calendar days to 30 business days, and town officials will have 20 business days, up from 14, to confirm a condition is met.
  • The Board of Health was added to the review of the final noise assessment.
  • The company must offer the fire department its first training on a 60-day timeline, with more time if the department or its mutual aid partners ask, and must tell the fire chief within five business days, down from 10, of any change in its emergency support contact, with no gap in coverage.

The company also told the board its remote operating center will watch the site at all times and can call police, that first responder stations with access codes sit at the gates, and that a licensed site professional will review the water used on any large fire and report on whether more cleanup steps are needed.

Public comment

The only member of the public who spoke Wednesday asked how residents can learn about upcoming meetings, and was told meeting notices are posted on the town's website in advance.

What happens next

The approval becomes final once the board reviews the written conditions, and no date for that review was set during the session. Under the state zoning law, a person aggrieved by a zoning board decision has 20 days after it is filed with the town clerk to appeal to court. South Coast 360 asked Town Planner Amy Messier, whose office staffs the board, on Thursday morning for the names of the two other voting members, when the board expects to review and sign the final conditions and file its written decision with the town clerk, and where the final conditions will be posted. Her answer will be added when it comes.

The peer reviewers' memos, the fire and police chiefs' letters, the company's plume study, noise study and site plans, and recordings of the hearing's sessions are posted on the town's Salt Cod Energy Storage project page. Questions about the petition go to the Office of the Town Planner at 508-646-2809.

Background on the hearing so far: our story on the Nov. 5 session and the plume study and our earlier look at the fire plan.

Label: Reported by us, from the town's posted records.

Notes

Every fact in this story comes from the town's own recording of the Nov. 18 Zoning Board of Appeals session on Somerset Access Television, which we heard in full on Nov. 19, the board's Nov. 18 agenda, the town's project page and the two peer reviewers' final memos posted there, the board's member list, Roux's own project page and the state zoning law, all read Nov. 19. We checked each date and weekday against a calendar. Two of the three voting members' names were not clear on the recording, so we name only the vice chair, who made the motion; South Coast 360 asked Town Planner Amy Messier for the other names on Nov. 19, and her answer will be added when it comes.

Corrections

No corrections to this story. If something here is wrong, tell us. Every correction is dated on the story and listed in our public log.

Sources (9)

  1. Somerset Zoning Board of Appeals, November 18, 2026 (Somerset Access Television, the town broadcast)Town recording of the Nov. 18 session, 2 hours 12 minutes, posted 11:44 p.m. Nov. 18. The reviewers, the sound wall, the conditions, public comment, the motion and the 3-0 roll call. Heard in full Nov. 19, 2026.
  2. Zoning Board of Appeals meeting agenda, Wednesday, Nov. 18, 2026 (clerk stamp Nov. 16, 2026, 12:27 p.m.)Town of Somerset, 1 page. Fairfield Inn and Suites, 602 G.A.R. Highway, 6 p.m.; public hearing on Somerset Energy Storage, LLC, 1606 Riverside Ave., Map B2, Lot 203, Section 6.10 planned development; signed Steven Moniz, Clerk. Read Nov. 19, 2026.
  3. Zoning Board of Appeals (Town of Somerset)Member list: Steven Cadorette, chair; Bernard Miranda, vice chair; Steven Moniz, clerk; two alternates. The building inspector is the zoning enforcement officer. Read Nov. 19, 2026.
  4. Power Plant Revitalization (Roux)Roux's project page: working on behalf of the Town of Somerset as an independent environmental adviser on the former Montaup Power Plant site. Read Nov. 19, 2026.
  5. Salt Cod Energy Storage B.E.S.S. Proposal (Town of Somerset)The town's project page: led by Flatiron Energy, up to 672 megawatt-hours; hearing sessions from April 9 to Nov. 18 (Nov. 12 canceled); the peer reviews, the fire and police letters, and the company's submissions. Read Nov. 19, 2026.
  6. Jensen Hughes, Comments on Revised Salt Cod BESS Plume Study, Rev. 2 (Town of Somerset)Final peer review memo: all 13 comments closed; a document-based review, models not rerun; comments 6 and 8 closed on Hazard Dynamics statements without the underlying results. Read Nov. 19, 2026.
  7. Roux, Technical Review of Planned Development Application, Memorandum 3, Nov. 11, 2026 (Town of Somerset)Final peer review memo to the board: comments 1 to 50 resolved or resolvable through conditions. Read Nov. 19, 2026.
  8. Staff Directory (Town of Somerset)Lists Jamison T. J. Barros as fire chief. Read Nov. 19, 2026.
  9. Massachusetts General Laws, Chapter 40A, Section 17Appeals of zoning board decisions: an action within 20 days after the decision is filed with the town clerk. Read Nov. 19, 2026.